Drilling indicator well - heat pump/ cooling system from 50kW

Drilling for the construction of extraction and absorption wells for groundwater heat pumps or cooling systems must be notified in good time before drilling work begins.

Description

Drilling into quaternary gravel layers and outside of water protection areas must be reported to the responsible authority. In the city of Munich, this is the Department for Climate and Environmental Protection.

The work can be started after a period of one month. The period begins with the receipt of the complete notification documents. The prerequisite is that the competent authority does not prohibit the drilling within this month

Important note

Important note

Boreholes that extend several metres into the deeper Tertiary strata(clay, silt, sand) require not only a drilling notification but also a permit under water law for boreholes subject to authorisation.

A separate water law permit is required for the operation of the groundwater heat pump or cooling system.

Required documents

The documents should preferably be submitted digitally.

  • Completed notification form
  • General site plan M 1:25,000 with marking of the location
  • Detailed site plan M 1:5,000 or M 1:1,000 with entry of the well locations

Duration and costs

Processing time

Maximum one month.

Legal basis

§ Section 49 of the Water Resources Act (BayWG)Article 30 of the Bavarian Water Act (BayWG)

Contact

Referat für Klima- und Umweltschutz
Sachgebiet Wasserrecht
Landeshauptstadt München

Postal address

Landeshauptstadt München
Referat für Klima- und Umweltschutz
Sachgebiet Wasserrecht

Bayerstraße 28a
80335 München

Address

Bayerstraße 28a
80335 München

Availability

  • Available:Wheelchair access
  • Not available:Disabled parking

Related services

Water law authorisation - service water wells

If you want to use groundwater for industrial water purposes, you need a permit under water law.

Drilling and working in groundwater

Drilling operations that reach so deep into the ground that they could come into contact with groundwater must be reported and, in some cases, require a permit

Report tree damage (during construction work)

If trees are damaged without authorisation, owners or polluters can be obliged to restore or plant replacement trees.

Completion of the replacement planting

If you have felled a tree, a replacement planting may be required as compensation. The completion of this replanting must be reported.

Water licence - heat pump/ cooling system up to 50kW

If you operate a heat pump or cooling system and extract or infiltrate groundwater via wells, you will need a permit under water law.

Water law permit - rainwater infiltration in water protection areas

A permit under water law is required for the infiltration of rainwater into the ground in a water protection area.

Water law permit - construction projects in groundwater

If you intervene in the groundwater during a construction project, a permit under water law is required.

Advice on the ecological criteria catalogue

If you want to build on a municipal property, you must comply with the ecological criteria catalogue of the City of Munich. We can advise you on this.